PROJECT STATUS
EMPLOYER
CATEGORY
PROJECT DURATION
PILE ELBUD SA also realizes out contracts for design works. One of such tasks is "Preparing complete design documentation together with obtaining the building permit decision for the project of: Construction of a 110kV line between Wygoda and Muchówka and Muchówka distribution substation" for Tauron Dystrybucja SA.
1. Drawing up the concept of technical solutions for the 110kV line and the land development plan for Muchówka distribution substation.
2. Development of legal documentation and detailed design.
3. Conclusion of notarial transmission easement agreements for the planned 110kV lines.
4. Purchase of the necessary area for the designed Muchówka substation.
5. Conclusion of notarial contracts of land easement for the access road to the designed Muchówka substation.