2018 - 2023
image

Project description:

The project is related to the planned Ostrołęka Power Plant C and will serve as a connection to the Ostrołęka 400/220/110kV substation. As part of the project, a single-circuit 400kV overhead line was constructed and a 110kV overhead line transitioning into a 440 metre-long cable line.

The new section of the line was made comprehensively - from the foundations, through the construction of poles, to the installation of conductors.

The designed 110kV cable line will constitute a backup power supply section for general needs of Ostrołęka Power Plant C.

  • design documentation
  • construction of foundations for poles
  • erection of the poles together with the execution of corrosion protection
  • installation of equipment and conductors of the 110kV line and laying of the 110kV cable
  • installation of equipment and conductors of the 400kV line
  • as-built documentation